********* ARE YOU MOVING TO RANKIN COUNTY? **********
If you are moving to the unincorporated area of Rankin County a utility permit is required to transfer electrical service into your name. Click HERE to obtain a utility permit application and instructions.
Inspections
There are 6 steps to an Inspection Procedure.
- Plumbing grounds (before plumber backfills ditches)
- Foundation (before concrete is poured - reverse for conventional foundation)
- Frame, Mechanical, Electrical rough-in (before insulation)
- Insulation
- Electrical Service (transfer of power from temporary to permanent).
** Must have form 910 from the Health Department approving sewer system
- Final Inspection