Inspections

There are 6 steps to an Inspection Procedure.

  1. Plumbing grounds (before plumber backfills ditches)

  2. Foundation (before concrete is poured - reverse for conventional foundation)

  3. Frame, Mechanical, Electrical rough-in (before insulation)

  4. Insulation

  5. Electrical Service (transfer of power from temporary to permanent).
    ** Must have form 910 from the Health Department approving sewer system

  6. Final Inspection